NASA stopped short of completing a critical fuel test for its Artemis 2 SLS rocket because of hydrogen leaks that sound a lot ...
The mission is meant to send four astronauts on a historic journey around the Moon and back, the first crewed flight of the ...
Four astronauts are to fly around the moon and back, but hydrogen leaks push planned launch to at least March Nasa's ...
NASA’s test run of its Artemis II countdown ran into problems Monday at Kennedy Space Center, scrapping any chance of the moonbound mission launching this month. Instead, the agency is targeting March ...
NASA defended preparations for Artemis 2 after a fueling test had hydrogen leaks like those that bedeviled Artemis 1 more ...
Shortly after 2 a.m. ET on Tuesday, NASA announced that it would forgo February’s launch window (which lasted until Feb. 11) for the Artemis II mission around the moon to allow teams to review data ...
NASA plans an on-pad repair of the fuel leak that derailed an overnight dress rehearsal countdown for the agency's huge ...
CAPE CANAVERAL, Fla. (AP) — NASA's long-awaited moonshot with astronauts is off until at least March because of hydrogen fuel leaks that marred the dress rehearsal of its giant new rocket.
Named after Apollo’s twin sister in Greek mythology, Artemis is meant to expand on NASA's Apollo missions of the 1960s and ...
The agency did not complete a practice countdown for a mission that would be the first to send people around the moon in more than 50 years.
After pre-launch testing revealed rocket issues, NASA has delayed the Artemis II launch until March. Here's the latest.
NASA said Tuesday it's delaying until March the launch of its first crewed flyby mission to the Moon in more than 50 years, ...